PILOT of $1,625 per MW annually
Company: IREN
The claim, verbatim
As additional consideration, Owner will pay the County an annual Payment in Lieu of Taxes equal to $1,625 multiplied by the certified Data Center Capacity during each of the ten abatement years, due October 1 each year.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Phase 3 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “in an amount equal to One thousand and six hundred twenty-five dollars ($1,625.00) multiplied by the total Data Center Capacity included in the Certificate”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Phase 3
Quote: “in an amount equal to One thousand and six hundred twenty-five dollars ($1,625.00) multiplied by the total Data Center Capacity included in the Certificate”