The agreement estimates that the Childress data center facility, if built to maximum capacity, will require approximately $592.5 million of capital investment.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Phase 2 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “It is estimated that, if built to its maximum capacity, the data center facility will require an estimated capital investment of approximately five hundred ninety-two million five hundred thousand dollars ($592,500,000.00).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Phase 2

Quote: “It is estimated that, if built to its maximum capacity, the data center facility will require an estimated capital investment of approximately five hundred ninety-two million five hundred thousand dollars ($592,500,000.00).”