IREN has started a community consultation for a proposed 900 MW greenfield data center campus at Redbank in New South Wales, outside its existing secured power portfolio.

Source (primary)

IREN (IREN) Starts Consultation On 900 MW Redbank Data Center Campus - Yahoo Finance (-, news_article)
View cached copy (2026-10-16)Live source ↗

Quote: “IREN (NasdaqGS: IREN) has started a community consultation for a proposed 900 MW data center campus at Redbank in New South Wales.”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The article states IREN started community consultation on a proposed 900 MW campus at Redbank, NSW, describes it as a greenfield site, and says it is outside the existing secured power portfolio.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/iren-iren-starts-consultation-900-150843079.html) in full (10,281 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN (IREN) Starts Consultation On 900 MW Redbank Data Center Campus - Yahoo Finance

Quote: “IREN (NasdaqGS: IREN) has started a community consultation for a proposed 900 MW data center campus at Redbank in New South Wales.”

View cached copy (2026-10-16)Live source ↗