327 MW current operating capacity

Company: Cipher Mining

Subject kind
facility capacity
Statement date
2025-05-05
Promised amount
327.0 MW
Current status
stated

The claim, verbatim

Cipher has 327 MW of operating capacity including JV capacity (Odessa 207 MW plus 120 MW at JV sites).

Source (primary)

cipher-mining 8-K exhibit (exh992ciphermining_busin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “327 MW Operating Capacity Including JV Capacity”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The document states 327 MW of operating capacity including JV capacity. It lists Odessa at 207 MW and the JV sites at 120 MW, which sum to 327 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000034/exh992ciphermining_busin.htm) in full (18,992 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (exh992ciphermining_busin.htm)

Quote: “327 MW Operating Capacity Including JV Capacity”

View cached copy (2026-10-16)Live source ↗