Hut 8 energized a direct-to-chip liquid-cooled test rack module at Salt Creek in preparation for Vega's energization.

Source (primary)

hut-8 8-K exhibit (hut-20250508xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “Energized a direct-to-chip liquid-cooled test rack module at Salt Creek in preparation for the energization of Vega.”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The release states Hut 8 energized a direct-to-chip liquid-cooled test rack module at Salt Creek in preparation for the energization of Vega.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000155837025006847/hut-20250508xex99d1.htm) in full (21,174 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms hut-8 8-K exhibit (hut-20250508xex99d1.htm)

Quote: “Energized a direct-to-chip liquid-cooled test rack module at Salt Creek in preparation for the energization of Vega.”

View cached copy (2026-10-15)Live source ↗