Promised amount
430000000.0 USD
Current status
stated

The claim, verbatim

Updated guidance puts total capex for the Core42 HPC buildout at $430 million (~$7.2M per critical MW, ~$6.0M per gross MW).

Source (primary)

terawulf 8-K exhibit (wulfq12025investorpresvf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “Total CapEx $430M”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

The HPC cost-to-build slide lists Total CapEx of $430M, ~$7.2M per critical MW and ~$6.0M per gross MW as updated guidance. That guidance is based on the 60 MW critical Core42 contract.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000033/wulfq12025investorpresvf.htm) in full (23,509 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)

Quote: “Total CapEx $430M”

View cached copy (2026-10-15)Live source ↗