Core42 60 MW HPC delivery
Company: TeraWulf
What the later record shows
Delivered late · happened March 31, 2026
At December 31, 2025 only 18 critical IT MW was energized. All 60 MW of Core42 leases had commenced by March 31, 2026.
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”
2026-05-07 · TeraWulf 10-Q filed 2026-05-08 View cached copy (2026-08-31)Live source ↗
Checked October 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is on track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025.
Source (primary)
terawulf 8-K exhibit (wulfq12025investorpresvf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗
Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
The presentation says TeraWulf is on track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025.
Confirmed in the source:
- TeraWulf is on track to deliver 60 MW of critical HPC hosting capacity
- The capacity is for Core42
- Delivery is targeted for 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000033/wulfq12025investorpresvf.htm) in full (23,509 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)
Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”
confirms TeraWulf 10-Q filed 2026-05-08
Quote: “All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”
confirms View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”