Contracted HPC capacity online 2025
Company: TeraWulf
What the later record shows
Delivered late · happened March 31, 2026
Only 18 critical IT MW was energized by year-end 2025. The full 60 MW Core42 capacity was delivered by March 31, 2026.
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“As of March 31, 2026, we had fully delivered CB-2, representing the full contracted capacity under the Core42 Leases currently in service.”
2026-05-07 · TeraWulf 10-Q filed 2026-05-08 View cached copy (2026-08-31)Live source ↗
Checked October 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
72.5 MW gross (60 MW net) of contracted HPC hosting capacity is expected to be online in 2025.
Source (primary)
terawulf 8-K exhibit (wulfq12025investorpresvf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗
Quote: “72.5 (gross) / 60 (net) MW contracted and expected online in 2025”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
The presentation states that 72.5 MW (gross) / 60 MW (net) is contracted and expected online in 2025.
Confirmed in the source:
- 72.5 MW gross of HPC hosting capacity is contracted
- 60 MW net of HPC hosting capacity is contracted
- The contracted HPC capacity is expected to be online in 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000033/wulfq12025investorpresvf.htm) in full (23,509 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)
Quote: “72.5 (gross) / 60 (net) MW contracted and expected online in 2025”
confirms TeraWulf 10-Q filed 2026-05-08
Quote: “As of March 31, 2026, we had fully delivered CB-2, representing the full contracted capacity under the Core42 Leases currently in service.”
confirms View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”