DC pipeline scalable to 1 GW+

Company: Nebius

Subject kind
facility capacity
Statement date
2025-05-19
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Nebius is building a data center pipeline intended to provide scalability to more than 1 GW.

Source (primary)

nebius 8-K exhibit (tm2515580d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-14)Live source ↗

Quote: “Building DC pipeline to provide scalability to 1 GW+”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

The medium-term outlook slide states that Nebius is building a DC pipeline to provide scalability to 1 GW+.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925050975/tm2515580d1_ex99-3.htm) in full (12,863 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2515580d1_ex99-3.htm)

Quote: “Building DC pipeline to provide scalability to 1 GW+”

View cached copy (2026-10-14)Live source ↗