B200 GPU rollout in Kansas City in Q2 2025
Company: Nebius
What the later record shows
Outcome not yet confirmed
The August 2025 release says Kansas City launched in April and added capacity in early July, but no passage says which GPUs were installed or mentions B200s.
“Our Kansas City data center officially launched in April and we added more compute capacity in early July.”
2025-08-06 · nebius 8-K exhibit (tm2522866d1_ex99-2.htm) View cached copy (2026-10-08)Live source ↗
Checked October 14, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Nebius will begin rolling out NVIDIA B200 GPUs at Kansas City in Q2 2025.
Source (primary)
nebius 8-K exhibit (tm2515580d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-14)Live source ↗
Quote: “We will start rolling out NVIDIA B200 GPUs in Q2'25.”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
The B200 rollout statement appears within the Kansas City entry and gives Q2 2025 as the timing.
Confirmed in the source:
- Nebius will start rolling out NVIDIA B200 GPUs at its Kansas City location in Q2 2025.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925050975/tm2515580d1_ex99-2.htm) in full (27,136 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms nebius 8-K exhibit (tm2515580d1_ex99-2.htm)
Quote: “We will start rolling out NVIDIA B200 GPUs in Q2'25.”