Apollo site target energization

Company: Cipher Mining - Project: Apollo Site

Subject kind
facility timeline
Statement date
2026-10-12
Promised by
2028-12-31
Promised amount
900.0 MW
Current status
stated

The claim, verbatim

Cipher acquired an option for a new Texas site, Apollo, for up to 900 MW, submitted as a studied load in ERCOT Batch Zero, with land secured, deposits funded and target energization in 2028.

Source (primary)

cipher-mining 8-K exhibit (d134900dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-14)Live source ↗

Quote: “Land secured and deposits funded, with target energization in 2028”

How we checked this

Checked on October 16, 2026. The cited source supports part of this claim, but not all of it.

The presentation confirms the Apollo option for up to 900 MW in Texas and its Batch Zero submission. The 'land secured and deposits funded, with target energization in 2028' text appears on the same slide, but the extracted layout does not clearly tie it to Apollo rather than the 1 GW Colchis site, which a later slide says is expected to energize in 2028.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000119312526419743/d134900dex991.htm) in full (17,922 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (d134900dex991.htm)

Quote: “Land secured and deposits funded, with target energization in 2028”

View cached copy (2026-10-14)Live source ↗