Contracted gross HPC capacity
Company: Cipher Mining
The claim, verbatim
Cipher has 700 MW of contracted gross HPC capacity as of September 30, 2026.
Source (primary)
cipher-mining 8-K exhibit (d134900dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-14)Live source ↗
Quote: “700 MW $16.6 Bn 17.3 Years $843 MM (3) (4) Contracted Gross HPC Capacity”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The overview slide lists 700 MW of contracted gross HPC capacity, and notes that all figures are as of September 30, 2026.
Confirmed in the source:
- Cipher has 700 MW of contracted gross HPC capacity
- The figure is as of September 30, 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000119312526419743/d134900dex991.htm) in full (17,922 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (d134900dex991.htm)
Quote: “700 MW $16.6 Bn 17.3 Years $843 MM (3) (4) Contracted Gross HPC Capacity”