Promised amount
907.0 MW
Current status
stated

The claim, verbatim

Cipher has 907 MW of operating and contracted capacity, including three data center campus leases with leading hyperscalers.

Source (primary)

cipher-mining 8-K exhibit (d134900dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-14)Live source ↗

Quote: “907 MW of operating and contracted capacity today, including three data center campus leases with the world’s leading hyperscalers”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The company overview slide states both figures directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000119312526419743/d134900dex991.htm) in full (17,922 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (d134900dex991.htm)

Quote: “907 MW of operating and contracted capacity today, including three data center campus leases with the world’s leading hyperscalers”