250 MW pending regulatory approval at Lake Mariner
Company: TeraWulf
The claim, verbatim
An additional 250 MW of power at Lake Mariner is pending regulatory approval.
Source (primary)
Fluidstack Deal Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗
Quote: “plus another 250 MW pending regulatory approval”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The announcement states that 250 MW of power at Lake Mariner, beyond the 500 MW already available, is pending regulatory approval.
Confirmed in the source:
- An additional 250 MW of power at Lake Mariner is pending regulatory approval
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23303/pdf/WULF_Fluidstack_Lease_Announcement_%28Aug_2025%29vF.pdf) in full (7,012 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Fluidstack Deal Presentation
Quote: “plus another 250 MW pending regulatory approval”