jain.com

250 MW pending regulatory approval at Lake Mariner

Company: TeraWulf

Subject kind
regulatory
Statement date
2025-08-14
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

An additional 250 MW of power at Lake Mariner is pending regulatory approval.

Source (primary)

Fluidstack Deal Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗

Quote: “plus another 250 MW pending regulatory approval”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The announcement states that 250 MW of power at Lake Mariner, beyond the 500 MW already available, is pending regulatory approval.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23303/pdf/WULF_Fluidstack_Lease_Announcement_%28Aug_2025%29vF.pdf) in full (7,012 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Fluidstack Deal Presentation

Quote: “plus another 250 MW pending regulatory approval”

View cached copy (2026-10-13)Live source ↗