Annual HPC leasing target

Company: TeraWulf

Subject kind
guidance
Statement date
2025-11-10
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

TeraWulf expects to lease 250-500 MW of critical IT load of new HPC capacity per year.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗

Quote: “Expect to lease 250-500 MW critical IT load of new HPC capacity per year”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The presentation states that TeraWulf expects to lease 250-500 MW of critical IT load of new HPC capacity each year.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Expect to lease 250-500 MW critical IT load of new HPC capacity per year”

View cached copy (2026-10-13)Live source ↗Archive.org ↗