PSC approval of 482 MW service agreement at Justified Data Campus
Company: TeraWulf
The claim, verbatim
In August, TeraWulf received approval for a Retail Electric Service Agreement to support 482 MW of electrical service at its Justified Data Campus in Kentucky.
Source (primary)
Amended Kentucky Power deal lifts TeraWulf’s Muskie campus to 1 GW - W.Media (-, news_article)
View cached copy (2026-10-09)Live source ↗Archive.org ↗
Quote: “TeraWulf received approval for a Retail Electric Service Agreement to support 482 MW of electrical service at its Justified Data Campus in Kentucky.”
How we checked this
Checked on October 14, 2026. The cited source supports part of this claim, but not all of it.
The article says w.media reported the approval in August, but it does not say when the approval was actually granted.
Confirmed in the source:
- TeraWulf received approval for a Retail Electric Service Agreement supporting 482 MW at its Justified Data Campus in Kentucky
- w.media reported this approval in August
We could not confirm this from the cited source:
- The approval itself was granted in August
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of the publisher (https://w.media/amended-kentucky-power-deal-lifts-terawulfs-muskie-campus-to-1-gw/) in full (7,116 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Amended Kentucky Power deal lifts TeraWulf’s Muskie campus to 1 GW - W.Media
Quote: “TeraWulf received approval for a Retail Electric Service Agreement to support 482 MW of electrical service at its Justified Data Campus in Kentucky.”