jain.com

Securing >1 GW power by end of 2026

Company: Nebius

Subject kind
facility capacity
Statement date
2025-08-06
Promised by
2026-12-31
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Nebius is targeting 1 GW of power in 2026 and is in the process of securing more than 1 GW of power by the end of 2026.

Source (primary)

nebius 8-K exhibit (tm2522866d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗

Quote: “Overall, we are in the process of securing more than 1 GW of power by the end of 2026.”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The letter states both the 1 GW target for 2026 and the effort to secure more than 1 GW by the end of 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925075028/tm2522866d1_ex99-2.htm) in full (32,613 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2522866d1_ex99-2.htm)

Quote: “Overall, we are in the process of securing more than 1 GW of power by the end of 2026.”

View cached copy (2026-10-08)Live source ↗

confirms nebius 8-K exhibit (tm2522866d1_ex99-1.htm)

Quote: “In the process of securing more than 1 GW of power by the end of 2026”

View cached copy (2026-10-08)Live source ↗