CB-2 delivery in Q4 2025
Company: TeraWulf
What the later record shows
The date slipped · new target December 31, 2026
Active HPC load at Q3 2025 was 18 MW, made up of Wulf Den and CB-1. Commenced capacity was still 18 MW at December 31, 2025, so CB-2 had not commenced in Q4 2025. The remaining leases are expected to commence in 2026.
“EOP Active Leased HPC Load (Net) 18 MW ➢ Wulf Den (2 MW net), CB-1 (16 MW net)”
2025-11-09 · terawulf 8-K exhibit (wulfq32025investorupdate.htm) View cached copy (2026-09-27)Live source ↗
“Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf expects to deliver CB-2 and begin generating revenue from it in Q4 2025.
Source (primary)
terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-07)Live source ↗
Quote: “and CB-2 in the fourth quarter, as previously guided”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The CEO's statement covers delivery and revenue generation for both CB-1 and CB-2 in a single sentence, with CB-2 expected in the fourth quarter. The release was issued in August 2025, so that quarter is Q4 2025.
Confirmed in the source:
- TeraWulf expects delivery of CB-2 in the fourth quarter of 2025.
- TeraWulf expects revenue generation from CB-2 to begin in the fourth quarter of 2025.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000058/a_wulfformearningsreleaseq.htm) in full (24,064 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm)
Quote: “and CB-2 in the fourth quarter, as previously guided”
delays TeraWulf 10-K filed 2026-02-27
Quote: “Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025.”
delays terawulf 8-K exhibit (wulfq32025investorupdate.htm)
Quote: “EOP Active Leased HPC Load (Net) 18 MW ➢ Wulf Den (2 MW net), CB-1 (16 MW net)”