Core42 72.5 MW HPC delivery in 2025

Company: TeraWulf

Subject kind
facility capacity
Statement date
2025-08-07
Promised by
2025-12-31
Promised amount
72.5 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered · new target March 31, 2026

By the Q4 2025 update, Wulf Den/CB-1 (18 MW) and CB-2A (21 MW) were delivered, while CB-2B (21 MW) was expected in Q1 2026. Only some Core42 leases commenced in 2025.

“Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf says it is on schedule and on budget to deliver 72.5 MW of gross HPC hosting infrastructure to Core42 in 2025.

Source (primary)

terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-07)Live source ↗

Quote: “On schedule and on budget to deliver 72.5 MW of gross HPC hosting infrastructure to Core42 in 2025.”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The headline of TeraWulf's Q2 2025 earnings release says this word for word.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000058/a_wulfformearningsreleaseq.htm) in full (24,064 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm)

Quote: “On schedule and on budget to deliver 72.5 MW of gross HPC hosting infrastructure to Core42 in 2025.”

View cached copy (2026-10-07)Live source ↗

Record of changes

October 7, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 8, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.