jain.com

Operational hashrate reached 50 EH/s

Company: CleanSpark

Subject kind
facility capacity
Statement date
2025-08-07
Current status
stated

The claim, verbatim

CleanSpark says it reached 50 EH/s of operational hashrate in June 2025, and claims to be the first public company to do so exclusively with American infrastructure.

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-07)Live source ↗

Quote: “We reached 50 EH/s of operational hashrate in June, becoming the first public company to do so exclusively with American infrastructure”

How we checked this

Checked on October 9, 2026. The cited source supports every part of this claim.

CEO Zach Bradford's quoted statement in the Q3 FY2025 results release says both things. The 'first public company' point is the company's own claim, not independently verified.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/827876/000095017025105347/clsk-ex99_1.htm) in full (18,099 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “We reached 50 EH/s of operational hashrate in June, becoming the first public company to do so exclusively with American infrastructure”

View cached copy (2026-10-07)Live source ↗