In an Aug. 21 final order, the Kentucky PSC approved an electric service agreement for TeraWulf's Justified campus in Hancock County with a 482 MW maximum contract demand and a six-year minimum demand obligation.

Source (primary)

TeraWulf doubles Muskie power agreement to 1 GW, plans 2029 delivery - Mugglehead Investment Magazine (-, news_article)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “In an Aug. 21 final order on TeraWulf's separate Justified campus in Hancock County, the commission approved an electric service agreement with a 482 MW maximum contract demand.”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The article reports the Aug. 21 order approving the Justified agreement at 482 MW, including a minimum demand obligation for the first six years.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://mugglehead.com/terawulf-muskie-kentucky-power-1gw-2029/) in full (8,299 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf doubles Muskie power agreement to 1 GW, plans 2029 delivery - Mugglehead Investment Magazine

Quote: “In an Aug. 21 final order on TeraWulf's separate Justified campus in Hancock County, the commission approved an electric service agreement with a 482 MW maximum contract demand.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗