jain.com

River Bend Phase II rezoning and site plan

Company: Hut 8

Subject kind
regulatory
Statement date
2026-10-06
Current status
stated

The claim, verbatim

Hut 8 sought rezoning and site plan approval for River Bend Phase II, which would develop about 180 acres with two buildings of about 568,000 square feet each plus substations and a switchyard, leaving the remainder undeveloped as a barrier.

Source (primary)

‘It’s going to be future-resilient.’ Get a look at the St. Francisville Hut 8 data center. - The Advocate (-, news_article)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Phase II would develop about 180 acres of the site, with the remaining amount staying untouched to act as a “barrier,” Matias DuRei with Hut 8 said. It would build two buildings of about 568,000 square feet each, with substations and a switchyard.”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The article reports the Phase II rezoning and site plan request and Hut 8's description of the acreage, buildings, substations, switchyard and barrier land.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.theadvocate.com/baton_rouge/news/communities/west_feliciana/st-francisville-data-center-construction-river-bend-hut8/article_4e6499a4-39b5-4137-9a32-b1bfd37a4dc4.html) in full (14,728 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms ‘It’s going to be future-resilient.’ Get a look at the St. Francisville Hut 8 data center. - The Advocate

Quote: “Phase II would develop about 180 acres of the site, with the remaining amount staying untouched to act as a “barrier,” Matias DuRei with Hut 8 said. It would build two buildings of about 568,000 square feet each, with substations and a switchyard.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗