Pipeline site delivery dates

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-08-04
Promised by
2030-12-31
Promised amount
2082.0 MW
Current status
stated

The claim, verbatim

Pipeline delivery targets: Lake Hawkeye ~320 MW in 2029, Lake Mariner expansion 162 MW in 2029, Chesapeake ~800 MW in 2030, Muskie ~800 MW in 2028–2030.

Source (primary)

Q2 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Total Critical IT ~320 MW Delivery 2029 Total Critical IT 162 MW Delivery 2029 Total Critical IT ~800 MW Delivery 2030 Total Critical IT ~800 MW Delivery 2028 – 2030”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The strategic campus slide lists these pipeline sites with the stated capacities and delivery years, and the Muskie timing is consistent with its appendix.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23522/pdf/TeraWulf+Q2+2026+Investor+Presentation.pdf) in full (28,349 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q2 2026 Earnings Update Presentation

Quote: “Total Critical IT ~320 MW Delivery 2029 Total Critical IT 162 MW Delivery 2029 Total Critical IT ~800 MW Delivery 2030 Total Critical IT ~800 MW Delivery 2028 – 2030”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2026-08-04.