CB-2 online timing
Company: TeraWulf
What the later record shows
Partly delivered · new target March 31, 2026
CB-2's estimated lease start moved from 11/30/25 to Q1 2026. CB-2A (21 MW) was delivered and CB-2B (21 MW) was expected in Q1 2026.
“Estimated Lease Start Date Prior Current Late Delivery Credits CB-2 11/30/25 Q1 None”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗
“CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-2 anticipated to come online around year-end 2025, subject to tenant fit-out requests.
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation states this timing and condition word for word.
Confirmed in the source:
- CB-2 is anticipated to come online around year-end 2025
- CB-2 timing is subject to tenant fit-out requests
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Investor Presentation
Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”