Abernathy build cost per MW

Company: TeraWulf

Subject kind
guidance
Statement date
2025-10-27
Promised amount
10000000.0 USD/MW
Current status
stated

The claim, verbatim

Build capex of $8MM-$10MM per MW of critical IT load.

Source (primary)

Majority-Owned Joint Venture with Fluidstack for 168 MW in Texas (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-10-06)Live source ↗

Quote: “Capex of $8MM-10MM per MW of critical IT load”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The presentation gives capex of $8MM to $10MM per MW of critical IT load for the Abernathy project.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23305/pdf/Abernathy_JV_Announcement_Pres_Oct_2025vF.pdf) in full (7,261 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Majority-Owned Joint Venture with Fluidstack for 168 MW in Texas

Quote: “Capex of $8MM-10MM per MW of critical IT load”

View cached copy (2026-10-06)Live source ↗

confirms Majority-Owned Joint Venture with Fluidstack for 168 MW in Texas

Quote: “Capex of $8MM-10MM per MW of critical IT load”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-10-27.