Capex $8-10MM per MW
Company: TeraWulf
The claim, verbatim
Capex expected at $8-$10 million per MW of critical IT load.
Source (primary)
WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-10-06)Live source ↗
Quote: “Capex of $8-$10MM per MW of critical IT load”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation lists capex of $8-$10MM per MW of critical IT load.
Confirmed in the source:
- Capex is $8-$10 million per MW of critical IT load
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23304/pdf/WULF_Expands_Fluidstack_Deal_August_2025.pdf) in full (11,936 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WULF Expands Fluidstack Deal
Quote: “Capex of $8-$10MM per MW of critical IT load”
