250 MW pending regulatory approval
Company: TeraWulf
The claim, verbatim
An additional 250 MW of power at Lake Mariner is pending regulatory approval.
Source (primary)
Fluidstack Deal Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗
Quote: “plus another 250 MW pending regulatory approval”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation states another 250 MW at Lake Mariner is pending regulatory approval.
Confirmed in the source:
- An additional 250 MW of power at Lake Mariner is pending regulatory approval
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23303/pdf/WULF_Fluidstack_Lease_Announcement_%28Aug_2025%29vF.pdf) in full (7,012 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Fluidstack Deal Presentation
Quote: “plus another 250 MW pending regulatory approval”