60 MW HPC hosting delivery to Core42 in 2025

Company: TeraWulf

Subject kind
customer
Statement date
2025-05-08
Promised by
2025-12-31
Promised amount
60.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

By December 31, 2025, only 18 critical IT MW of the 60 MW Core42 capacity had commenced. The remainder was expected in 2026.

“Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
“The remainder of the HPC Leases are expected to commence in 2026.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf is on track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗

Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The operations summary states this directly.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”

View cached copy (2026-10-06)Live source ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-05-08.