jain.com

150-200 MW new HPC capacity per year

Company: TeraWulf

Subject kind
guidance
Statement date
2025-08-13
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

TeraWulf expects to deploy 150-200 MW of new HPC capacity annually.

Source (primary)

terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗

Quote: “Expect to deploy 150 - 200 MW of new HPC capacity per year”

How we checked this

Checked on October 7, 2026. The cited source supports every part of this claim.

The presentation states this expectation directly, and repeats it on the capacity overview slide.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)

Quote: “Expect to deploy 150 - 200 MW of new HPC capacity per year”

View cached copy (2026-10-06)Live source ↗