150-200 MW new HPC capacity per year
Company: TeraWulf
The claim, verbatim
TeraWulf expects to deploy 150-200 MW of new HPC capacity annually.
Source (primary)
terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “Expect to deploy 150 - 200 MW of new HPC capacity per year”
How we checked this
Checked on October 7, 2026. The cited source supports every part of this claim.
The presentation states this expectation directly, and repeats it on the capacity overview slide.
Confirmed in the source:
- TeraWulf expects to deploy 150-200 MW of new HPC capacity per year
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “Expect to deploy 150 - 200 MW of new HPC capacity per year”