Fluidstack HPC lease 250 MW online 2026
Company: TeraWulf
The claim, verbatim
TeraWulf has 250 MW of gross HPC capacity contracted to Fluidstack, expected to be online in 2026.
Source (primary)
terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “250.0 MW contracted to Fluidstack (online 2026)”
How we checked this
Checked on October 7, 2026. The cited source supports every part of this claim.
The presentation lists 250.0 MW contracted to Fluidstack, online in 2026, and notes that MW figures are gross capacity.
Confirmed in the source:
- TeraWulf has 250 MW of HPC capacity contracted to Fluidstack
- The Fluidstack capacity is expected online in 2026
- The 250 MW figure is gross capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “250.0 MW contracted to Fluidstack (online 2026)”