Additional 250 MW pending regulatory approval
Company: TeraWulf
The claim, verbatim
An additional 250 MW at Lake Mariner is pending regulatory approval, which would bring total power to 750 MW.
Source (primary)
terawulf 8-K exhibit (tm2523008d2_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “plus another 250 MW pending regulatory approval (750 MW total)”
How we checked this
Checked on October 7, 2026. The cited source supports every part of this claim.
The Lake Mariner slide states there is another 250 MW pending regulatory approval, for 750 MW total.
Confirmed in the source:
- An additional 250 MW at Lake Mariner is pending regulatory approval
- With that addition, total power would be 750 MW
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-2.htm) in full (7,456 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d2_ex99-2.htm)
Quote: “plus another 250 MW pending regulatory approval (750 MW total)”