Capex $8-10MM per MW
Company: TeraWulf
The claim, verbatim
Capex is expected to be $8-$10M per MW of critical IT load.
Source (primary)
terawulf 8-K exhibit (tm2523008d2_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “Capex of $8 - $10MM per MW of critical IT load”
How we checked this
Checked on October 7, 2026. The cited source supports every part of this claim.
The deal economics slide lists capex of $8-$10MM per MW of critical IT load.
Confirmed in the source:
- Capex is $8-$10M per MW of critical IT load
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-2.htm) in full (7,456 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2523008d2_ex99-2.htm)
Quote: “Capex of $8 - $10MM per MW of critical IT load”