Beacon Point 1,000 MW interconnection

Company: Hut 8 - Project: Beacon Point

Subject kind
facility capacity
Statement date
2026-09-28
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Beacon Point holds a 1,000 MW interconnection agreement with AEP Texas.

Source (primary)

Hut 8 Closes Two-Tier AI Data Center Finance Stack; JPMorgan Leads 12-Bank Revolver - Tech Times (-, news_article)
View cached copy (2026-10-05)Live source ↗Archive.org ↗

Quote: “The campus holds a 1,000 megawatt interconnection agreement with AEP Texas”

How we checked this

Checked on October 7, 2026. The cited source supports every part of this claim.

The article states that the Beacon Point campus holds a 1,000 MW interconnection agreement with AEP Texas.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.techtimes.com/articles/328138/20260928/hut-8-closes-two-tier-ai-data-center-finance-stack-jpmorgan-leads-12-bank-revolver.htm) in full (17,743 characters, retrieved October 5, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 Closes Two-Tier AI Data Center Finance Stack; JPMorgan Leads 12-Bank Revolver - Tech Times

Quote: “The campus holds a 1,000 megawatt interconnection agreement with AEP Texas”

View cached copy (2026-10-05)Live source ↗Archive.org ↗