Tarbush potential expansion to 300 MW

Company: Hut 8 - Project: Tarbush

Subject kind
facility timeline
Statement date
2026-09-30
Promised by
2029-12-31
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

The Tarbush agreement contemplates potential expansion to 300 MW by the end of 2029.

Source (primary)

Poolin Auction Reopens as Hut 8 Deal Ties $80 Million to Data Center Milestones - TheEnergyMag (-, news_article)
View cached copy (2026-10-05)Live source ↗Archive.org ↗

Quote: “contemplates potential expansion to 300 megawatts by the end of 2029”

How we checked this

Checked on October 7, 2026. The cited source supports every part of this claim.

The article states the agreement contemplates this potential expansion. It also notes that this is potential capacity, not an operating campus.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://theenergymag.com/news/2026-09-30/poolin-hut8-bid-reopen) in full (5,928 characters, retrieved October 5, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Poolin Auction Reopens as Hut 8 Deal Ties $80 Million to Data Center Milestones - TheEnergyMag

Quote: “contemplates potential expansion to 300 megawatts by the end of 2029”

View cached copy (2026-10-05)Live source ↗Archive.org ↗