Estimated project cost $9-11M per MW

Company: Cipher Mining

Subject kind
guidance
Statement date
2025-09-24
Current status
stated

The claim, verbatim

Cipher estimates project costs of $9-$11 million per MW of critical IT load.

Source (primary)

cipher-mining 8-K exhibit (dp234624_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-01)Live source ↗

Quote: “Estimated project costs of $9-$11 million per MW of critical IT load”

How we checked this

Checked on October 2, 2026. The cited source supports every part of this claim.

The transaction details in the release list estimated project costs of $9-$11 million per MW of critical IT load.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010325012168/dp234624_ex9901.htm) in full (12,064 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (dp234624_ex9901.htm)

Quote: “Estimated project costs of $9-$11 million per MW of critical IT load”

View cached copy (2026-10-01)Live source ↗