CEO says NY data center moratorium does not affect Lake Mariner or Cayuga
Company: TeraWulf
The claim, verbatim
CEO Paul Prager said on X that Lake Mariner and Lake Hawkeye/Cayuga are not affected by New York Governor Hochul's executive order pausing new hyperscale data center permits, and called the order a positive step.
Source (primary)
Why WULF Stock Is Rebounding Today? This Analyst Says Core Data Center Project Avoids New York Permit Freeze - Stocktwits (-, news_article)
View cached copy (2026-09-28)Live source ↗Archive.org ↗
Quote: “CEO Paul Prager struck a more optimistic note on X on Tuesday, saying that Lake Mariner and Lake Hawkeye/Cayuga are not affected by the executive order and calling it “a positive step.””
How we checked this
Checked on September 30, 2026. The cited source supports every part of this claim.
The article reports that Prager said on X that both sites are unaffected by Hochul's order, which halts new permits for hyperscale data centers, and called it a positive step.
Confirmed in the source:
- TeraWulf CEO Paul Prager posted on X
- Prager said Lake Mariner and Lake Hawkeye/Cayuga are not affected by the executive order
- Governor Hochul's executive order stops new state environmental permits and is described as a moratorium on new hyperscale data centers
- Prager called the order a positive step
What we did: Read our cached copy of the publisher (https://stocktwits.com/news-articles/markets/equity/wulf-stock-rebound-meedham-analyst-new-york-executive-order/cZZ2zP7R7AX) in full (5,796 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Why WULF Stock Is Rebounding Today? This Analyst Says Core Data Center Project Avoids New York Permit Freeze - Stocktwits
Quote: “CEO Paul Prager struck a more optimistic note on X on Tuesday, saying that Lake Mariner and Lake Hawkeye/Cayuga are not affected by the executive order and calling it “a positive step.””