jain.com

800 MW deployed by 2025, >23 EH/s

Company: TeraWulf

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2021-10-01
Promised by
2025-12-31
Promised amount
800.0 MW
Current status
delayed

What the later record shows

The date slipped

By November 2025 TeraWulf reported only about 130 MW of bitcoin mining in operation and an 11.6 EH/s end-of-Q3 hash rate. That is far short of 800 MW and over 23 EH/s by 2025, and no new date was given.

“HPC Colocation | 594 MW contracted1 Bitcoin Mining | ~130 MW Expect to lease 250-500 MW critical IT load of new HPC capacity per year”
2025-11-09 · terawulf 8-K exhibit (wulfq32025investorupdate.htm) View cached copy (2026-09-27)Live source ↗
“End of Period Hash Rate 11.6 EH/s ➢ Represents a 53% increase YoY”
2025-11-09 · terawulf 8-K exhibit (wulfq32025investorupdate.htm) View cached copy (2026-09-27)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Complaint quotes TeraWulf's press release saying it expected 800 MW of mining capacity deployed by 2025, enabling over 23 EH/s of hashrate.

Source (primary)

Jacobs v. Ikonics Corporation — Entry #1: COMPLAINT against Marianne Bohren, Lockwood Carlson, Jeffrey D (RECAP, court_filing)
View cached copy (2026-09-28)Live source ↗

Quote: “expects to have 800 MW mining capacity deployed by 2025, enabling over 23 EH/s of expected hashrate”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The quoted press release states both the 800 MW by 2025 target and the over 23 EH/s expected hashrate.

Confirmed in the source:

What we did: Read our cached copy of RECAP (https://archive.org/download/gov.uscourts.nysd.567446/gov.uscourts.nysd.567446.1.0.pdf) in full (25,949 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Jacobs v. Ikonics Corporation — Entry #1: COMPLAINT against Marianne Bohren, Lockwood Carlson, Jeffrey D

Quote: “expects to have 800 MW mining capacity deployed by 2025, enabling over 23 EH/s of expected hashrate”

View cached copy (2026-09-28)Live source ↗

delays terawulf 8-K exhibit (wulfq32025investorupdate.htm)

Quote: “HPC Colocation | 594 MW contracted1 Bitcoin Mining | ~130 MW Expect to lease 250-500 MW critical IT load of new HPC capacity per year”

View cached copy (2026-09-27)Live source ↗

Record of changes

September 28, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 29, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-28 was the source's retrieval date; source published 2021-10-01.
October 9, 2026 — delayed