800 MW deployed by 2025, >23 EH/s
Company: TeraWulf
What the later record shows
The date slipped
By November 2025 TeraWulf reported only about 130 MW of bitcoin mining in operation and an 11.6 EH/s end-of-Q3 hash rate. That is far short of 800 MW and over 23 EH/s by 2025, and no new date was given.
“HPC Colocation | 594 MW contracted1 Bitcoin Mining | ~130 MW Expect to lease 250-500 MW critical IT load of new HPC capacity per year”
2025-11-09 · terawulf 8-K exhibit (wulfq32025investorupdate.htm) View cached copy (2026-09-27)Live source ↗
“End of Period Hash Rate 11.6 EH/s ➢ Represents a 53% increase YoY”
2025-11-09 · terawulf 8-K exhibit (wulfq32025investorupdate.htm) View cached copy (2026-09-27)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Complaint quotes TeraWulf's press release saying it expected 800 MW of mining capacity deployed by 2025, enabling over 23 EH/s of hashrate.
Source (primary)
Jacobs v. Ikonics Corporation — Entry #1: COMPLAINT against Marianne Bohren, Lockwood Carlson, Jeffrey D (RECAP, court_filing)
View cached copy (2026-09-28)Live source ↗
Quote: “expects to have 800 MW mining capacity deployed by 2025, enabling over 23 EH/s of expected hashrate”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The quoted press release states both the 800 MW by 2025 target and the over 23 EH/s expected hashrate.
Confirmed in the source:
- The complaint quotes TeraWulf's press release saying it expected 800 MW of mining capacity deployed by 2025
- The release says this capacity would enable over 23 EH/s of hashrate
What we did: Read our cached copy of RECAP (https://archive.org/download/gov.uscourts.nysd.567446/gov.uscourts.nysd.567446.1.0.pdf) in full (25,949 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Jacobs v. Ikonics Corporation — Entry #1: COMPLAINT against Marianne Bohren, Lockwood Carlson, Jeffrey D
Quote: “expects to have 800 MW mining capacity deployed by 2025, enabling over 23 EH/s of expected hashrate”
delays terawulf 8-K exhibit (wulfq32025investorupdate.htm)
Quote: “HPC Colocation | 594 MW contracted1 Bitcoin Mining | ~130 MW Expect to lease 250-500 MW critical IT load of new HPC capacity per year”