Commercial gasifier readiness target

Company: CleanSpark

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
product
Statement date
2015-12-28
Promised by
2016-06-30
Current status
delayed

What the later record shows

The date slipped

The December 2016 10-K said the Gasifier was still under development and moved the sellable date to Q4 2017. Later filings dropped any date and said no significant resources would go to gasification.

“Our Gasifier is still under development and a commercially viable Gasifier is not expected to be sellable until the fourth quarter of 2017.”
2016-12-29 · CleanSpark 10-K filed 2016-12-30 View cached copy (2026-09-27)Live source ↗
“Our prototype gasifier is still under development and a commercially viable gasifier is not expected to be viable for sale until we expend additional resources”
2021-08-15 · CleanSpark 10-Q filed 2021-08-16 View cached copy (2026-09-13)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Commercially viable gasifier not expected to be sellable until mid-year 2016

Source (primary)

CleanSpark 10-K filed 2015-12-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “Our Gasifier is still under development and a commercially viable Gasifier is not expected to be sellable until mid-year 2016.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The 10-K states that a commercially viable Gasifier is not expected to be sellable until mid-year 2016.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166225215000002/mainbody.htm) in full (113,996 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2015-12-29

Quote: “Our Gasifier is still under development and a commercially viable Gasifier is not expected to be sellable until mid-year 2016.”

View cached copy (2026-09-27)Live source ↗

delays CleanSpark 10-Q filed 2021-08-16

Quote: “Our prototype gasifier is still under development and a commercially viable gasifier is not expected to be viable for sale until we expend additional resources”

View cached copy (2026-09-13)Live source ↗

delays CleanSpark 10-K filed 2016-12-30

Quote: “Our Gasifier is still under development and a commercially viable Gasifier is not expected to be sellable until the fourth quarter of 2017.”

View cached copy (2026-09-27)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 28, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.