Annual HPC capacity leasing target
Company: TeraWulf
The claim, verbatim
TeraWulf expects to lease 250-500 MW of critical IT load of new HPC capacity per year going forward
Source (primary)
terawulf 8-K exhibit (wulfq32025investorupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗
Quote: “Expect to lease 250-500 MW critical IT load of new HPC capacity per year”
How we checked this
Checked on September 28, 2026. The cited source supports every part of this claim.
The presentation states TeraWulf expects to lease 250-500 MW of critical IT load of new HPC capacity per year. It repeats this as an expected annual rate of incremental HPC signings.
Confirmed in the source:
- TeraWulf expects to lease 250-500 MW of critical IT load of new HPC capacity per year
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000096/wulfq32025investorupdate.htm) in full (31,516 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (wulfq32025investorupdate.htm)
Quote: “Expect to lease 250-500 MW critical IT load of new HPC capacity per year”