CB-2 facility anticipated online

Company: TeraWulf

Subject kind
facility timeline
Statement date
2025-11-09
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026

In February 2026, CB-2's lease start had moved from 11/30/25 to Q1 2026, with only CB-2A (21 MW) delivered. The company later reported CB-2 fully delivered as of March 31, 2026, which is after year-end 2025.

“CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗
“As of March 31, 2026, TeraWulf had fully delivered CB-2, with all Core42 capacity across the Wulf Den, CB-1 and CB-2 generating revenue.”
2026-04-13 · terawulf 8-K exhibit (tm2611661d4_ex99-1.htm) View cached copy (2026-09-10)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 facility anticipated to come online around year-end 2025, subject to tenant fit-out requests

Source (primary)

terawulf 8-K exhibit (wulfq32025investorupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The presentation says CB-2 was anticipated to come online around year-end 2025, subject to tenant fit-out requests.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000096/wulfq32025investorupdate.htm) in full (31,516 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfq32025investorupdate.htm)

Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”

View cached copy (2026-09-27)Live source ↗

confirms Q4 Earnings Update Presentation

Quote: “CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”

View cached copy (2026-09-01)Live source ↗

confirms terawulf 8-K exhibit (tm2611661d4_ex99-1.htm)

Quote: “As of March 31, 2026, TeraWulf had fully delivered CB-2, with all Core42 capacity across the Wulf Den, CB-1 and CB-2 generating revenue.”

View cached copy (2026-09-10)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 27, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.