$3.2B Senior Secured Green Notes
Company: TeraWulf
The claim, verbatim
TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par to finance construction of 522.5 MW of AI/HPC data centers at Lake Mariner Campus
Source (primary)
terawulf 8-K exhibit (wulfq32025investorupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗
Quote: “On October 16th, TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par to finance the construction of 522.5 MW of AI / High Powered Compute Data Centers at our Flagship Lake Mariner Campus”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfq32025investorupdate.htm)
Quote: “On October 16th, TeraWulf priced a $3.2 billion offering of 7.750% senior secured notes due 2030 at par to finance the construction of 522.5 MW of AI / High Powered Compute Data Centers at our Flagship Lake Mariner Campus”