Company: Nebius

Subject kind
facility capacity
Statement date
2025-11-11
Promised by
2026-12-31
Promised amount
800.0 MW
Current status
stated

The claim, verbatim

Expect 800 MW to 1 GW of connected power by end of 2026, representing power connected to built data centers

Source (primary)

nebius 8-K exhibit (tm2530882d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-26)Live source ↗

Quote: “Of this contracted amount, we expect to have 800MW to 1GW of connected power (i.e, power connected to built data centers) by the end of 2026”

How we checked this

Checked on September 28, 2026. The cited source supports every part of this claim.

The letter gives the 800 MW–1 GW connected power expectation for end of 2026 along with its definition.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925109806/tm2530882d1_ex99-2.htm) in full (39,078 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2530882d1_ex99-2.htm)

Quote: “Of this contracted amount, we expect to have 800MW to 1GW of connected power (i.e, power connected to built data centers) by the end of 2026”

View cached copy (2026-09-26)Live source ↗