Data Center Lease Commencement
Company: TeraWulf
What the later record shows
Outcome not yet confirmed
No passage names this data center lease or says whether it commenced on September 30, 2026. The Fluidstack lease updates in the passages cannot be tied to it.
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The data center lease is scheduled to commence on September 30, 2026
Source (primary)
terawulf 8-K exhibit (tm2533871d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗
Quote: “DC Lease commences 9/30/2026”
How we checked this
Checked on October 2, 2026. The cited source supports part of this claim, but not all of it.
The document gives 9/30/2026 as the lease commencement date only as one of its 'Key Model Assumptions' for projected cash flows. It does not say the lease is contractually scheduled to begin on that date.
Confirmed in the source:
- The investor presentation's cash flow model assumes the data center (DC) lease commences on September 30, 2026
We could not confirm this from the cited source:
- That September 30, 2026 is the contractually scheduled commencement date of the data center lease, rather than an assumption used for illustrative financial modeling
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925122387/tm2533871d1_ex99-1.htm) in full (12,131 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (tm2533871d1_ex99-1.htm)
Quote: “DC Lease commences 9/30/2026”