jain.com

Development cost intensity

Company: CleanSpark

Subject kind
facility capacity
Statement date
2026-09-17
Promised amount
11.9 million USD/MW
Current status
stated

The claim, verbatim

Development costs are approximately $11.9 million per MW of critical IT capacity

Source (primary)

CleanSpark Reveals Meta Behind $6.6 Billion AI Lease, Requires $2.23 Billion Financing - the deep dive (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “CleanSpark's September presentation puts development costs at roughly $11.9 million per MW of critical IT capacity”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The article cites CleanSpark's September presentation putting development costs at about $11.9 million per MW of critical IT capacity.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://thedeepdive.ca/cleanspark-reveals-meta-behind-6-6-billion-ai-lease-requires-2-23-billion-financing/) in full (9,051 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Reveals Meta Behind $6.6 Billion AI Lease, Requires $2.23 Billion Financing - the deep dive

Quote: “CleanSpark's September presentation puts development costs at roughly $11.9 million per MW of critical IT capacity”

View cached copy (2026-09-20)Live source ↗