ERCOT and Oncor approvals for Black Pearl

Company: Cipher Mining

Subject kind
regulatory
Statement date
2026-02-02
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Black Pearl has executed a 300 MW Facility Extension Agreement with Oncor and received ERCOT approval without pending approvals or load profile restrictions.

Source (primary)

cipher-mining 8-K exhibit (dp240991_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-20)Live source ↗

Quote: “300 MW Facility Extension Agreement executed with Oncor and approved by ERCOT, without any pending approvals or restrictions on the load profile”

How we checked this

Checked on September 24, 2026. The cited source supports every part of this claim.

The document states a 300 MW Facility Extension Agreement was executed with Oncor and approved by ERCOT, with no pending approvals or load profile restrictions.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010326001480/dp240991_ex9901.htm) in full (20,147 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (dp240991_ex9901.htm)

Quote: “300 MW Facility Extension Agreement executed with Oncor and approved by ERCOT, without any pending approvals or restrictions on the load profile”

View cached copy (2026-09-20)Live source ↗