jain.com

Sandersville Rent Commencement

Company: CleanSpark

Subject kind
facility timeline
Statement date
2026-09-16
Promised by
2027-11-30
Current status
stated

The claim, verbatim

Sandersville Phase I targeted to begin rent revenue on November 30, 2027, after completion of the first network hall

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-18)Live source ↗

Quote: “Rent revenue begins November 30, 2027 after the first network hall is completed”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “Rent revenue begins November 30, 2027 after the first network hall is completed”

View cached copy (2026-09-18)Live source ↗