jain.com

Active miners installed at Oklahoma City data center

Company: Riot - Project: Oklahoma City

Subject kind
facility capacity
Statement date
2018-08-13
Promised amount
8000.0 units
Current status
stated

The claim, verbatim

As of June 30, 2018, approximately 8,000 miners were installed and operating at the Oklahoma City data center facility

Source (primary)

Riot 10-Q filed 2018-08-14 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “As of June 30, 2018, approximately 8,000 miners were installed and operating”

How we checked this

Checked on September 23, 2026. The cited source supports every part of this claim.

The filing says the Company began consolidating all of its miners at the Oklahoma City data center after the lease was signed and that about 8,000 were installed and operating as of June 30, 2018. It also says the mining operations are located in Oklahoma City.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000107997318000474/riot_10q-063018.htm) in full (125,486 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-Q filed 2018-08-14

Quote: “As of June 30, 2018, approximately 8,000 miners were installed and operating”

View cached copy (2026-09-13)Live source ↗