jain.com

Camp Pendleton microgrid installation expected completion early 2019

Company: CleanSpark - Project: Camp Pendleton

Subject kind
facility timeline
Statement date
2019-01-14
Promised by
2019-03-31
Current status
verified

What the later record shows

Delivered late · happened May 31, 2019

The promised completion was early 2019 (by end of March). The May 2019 10-Q says the scope of work was completed in May 2019, and a May 3, 2019 8-K announced government acceptance of the microgrid.

“we issued a press release announcing the government acceptance of our solar plus storage microgrid located at the Marine Corps Base Camp Pendleton.”
2019-05-02 · CleanSpark 8-K filed 2019-05-03 View cached copy (2026-09-13)Live source ↗
“The Company began on-site work for this project in February of 2018 and completed its scope of work in May 2019.”
2019-05-14 · CleanSpark 10-Q filed 2019-05-15 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company expects to complete Camp Pendleton microgrid installation scope of work in early 2019, with on-site work begun February 2018

Source (primary)

CleanSpark 10-K filed 2019-01-15 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states that on-site work on the Camp Pendleton microgrid subcontract began in February 2018 and that the company expected to complete its scope of work in early 2019.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166357719000036/mainbody2.htm) in full (251,181 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2019-01-15

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019”

View cached copy (2026-09-13)Live source ↗

confirms CleanSpark 10-K filed 2019-01-15

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019.”

View cached copy (2026-09-27)Live source ↗

confirms CleanSpark 10-Q filed 2019-05-15

Quote: “The Company began on-site work for this project in February of 2018 and completed its scope of work in May 2019.”

View cached copy (2026-09-13)Live source ↗

confirms CleanSpark 8-K filed 2019-05-03

Quote: “we issued a press release announcing the government acceptance of our solar plus storage microgrid located at the Marine Corps Base Camp Pendleton.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.