jain.com

Camp Pendleton microgrid installation expected completion early 2019

Company: CleanSpark - Project: Camp Pendleton

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2019-01-14
Promised by
2019-03-31
Current status
delayed

The claim, verbatim

Company expects to complete Camp Pendleton microgrid installation scope of work in early 2019, with on-site work begun February 2018

Source (primary)

CleanSpark 10-K filed 2019-01-15 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 10-K filed 2019-01-15

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed