Remaining S19-Pro miners delivery schedule

Company: Riot

Subject kind
facility timeline
Statement date
2020-10-06
Promised amount
13100.0 units
Current status
stated

The claim, verbatim

Remaining 13,100 miners to be delivered in monthly installments starting in first half of 2021

Source (primary)

Riot S-3 filed 2020-10-07 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “the remaining 13,100 miners to be delivered in monthly installments starting during the first half of 2021”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot S-3 filed 2020-10-07

Quote: “the remaining 13,100 miners to be delivered in monthly installments starting during the first half of 2021”

View cached copy (2026-09-13)Live source ↗