Land lease for facility construction and access
Company: Marathon Digital - Project: Hardin
The claim, verbatim
Marathon has the right to construct and access the facility on land adjacent to the Hardin Station at no additional cost pursuant to a lease agreement with Beowulf
Source (primary)
Marathon Digital 8-K filed 2020-10-13 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Marathon has the right, at no additional cost, to construct and access the Facility on land adjacent to the Hardin Station pursuant to a lease agreement with Beowulf”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Marathon Digital 8-K filed 2020-10-13
Quote: “Marathon has the right, at no additional cost, to construct and access the Facility on land adjacent to the Hardin Station pursuant to a lease agreement with Beowulf”